COCOMO Software Effort Estimator (Basic COCOMO)
Effort in person-months, development time, average team size, productivity and cost of a software project from its size in thousands of lines of code, using Boehm's Basic COCOMO.
Results
The dashed line marks the value you entered.
What this tool does
Barry Boehm's Basic COCOMO (1981) estimates effort from size alone: Effort = a × KLOC^b, with a and b depending on the kind of project, followed by Time = 2.5 × Effort^d. Because b is above 1, effort grows faster than size, a sign that large projects lose productivity to communication, and because d is only about a third, doubling the team does not halve the time. 50 KLOC in an organic project comes to about 146 person-months over some 17 months. It was calibrated on 63 projects of the 1970s; use it for order-of-magnitude planning, not as a promise.
Formula
Effort = a × KLOC^b [person-months] · Time = 2.5 × Effort^d [months] · Team = Effort ÷ Time (Basic COCOMO: organic 2.4/1.05/0.38, semi-detached 3.0/1.12/0.35, embedded 3.6/1.20/0.32)
Variables
| Symbol | Meaning | Unit |
|---|---|---|
kl | Size of the software | KLOC |
md | Type of project | — |
cpm | Cost of one person-month | — |
EF | Effort | person-months |
DU | Development time | months |
TE | Average team size | — |
PR | Productivity | LOC/person-month |
CO | Cost of the development | — |
Worked example
- Size of the software50 KLOC
- Type of project1
- Cost of one person-month6000
- Effort145.9 person-months
- Development time16.6 months
- Average team size8.8
- Productivity343 LOC/person-month
- Cost of the development875,550
Limitations
- The result is an estimate based only on the values you type. Real situations often include factors this calculator does not know about.
- The default values are typical reference figures, not measurements of your situation. Replace them with your own data whenever you have it.