Line Balancing and Takt Time Calculator

Takt time, theoretical number of workstations and balance efficiency of an assembly line.

Results

Workstations 3
Takt time 90.00 s
Balance efficiency 117.65 %
Capacity 397 un

What this tool does

Takt time is the drumbeat the customer sets: available time divided by the units they want. Dividing the total hands-on work by that beat gives the minimum number of stations, and comparing it with the slowest station shows how much capacity is being lost to imbalance.

Formula

takt = available time ÷ demand ; stations = work total ÷ takt

Variables

SymbolMeaningUnit
taAvailable working timemin
dmDemandun
wcTotal work contents
btSlowest station times
NSWorkstations
TKTakt times
EBBalance efficiency%
CACapacityun

Worked example

  • Available working time450 min
  • Demand300 un
  • Total work content240 s
  • Slowest station time68 s
  • Workstations3
  • Takt time90.00 s
  • Balance efficiency117.65 %
  • Capacity397 un

Limitations

  • The result is an estimate based only on the values you type. Real situations often include factors this calculator does not know about.
  • The formula assumes ideal conditions: no friction losses, no air resistance and no efficiency losses unless you enter them.