Standard Cost Variance Calculator (Material and Labour Price, Usage and Efficiency)
Material price and usage variances and labour rate and efficiency variances from standard and actual figures, with the total difference from the standard cost.
Results
What this tool does
Standard costing sets what a unit of output should cost, then explains the gap to what it really cost. Each cost splits into a price effect (paid more or less per unit, measured on the actual quantity) and a quantity effect (used more or less than allowed, measured at the standard price), and the two always add up to the total. Positive figures here mean actual cost above standard, called adverse; negative ones are favourable. A variance only says where to look, not why: a cheap supplier can cause a favourable price variance and an adverse usage variance at once. Here the quantity bought is taken to equal the quantity used.
Formula
price variance = (actual price − std price) × actual qty · usage variance = (actual qty − std qty) × std price
Variables
| Symbol | Meaning | Unit |
|---|---|---|
m1 | Material: standard price per unit | — |
m2 | Material: actual price paid per unit | — |
m3 | Material: quantity allowed for the actual output | — |
m4 | Material: quantity actually used | — |
l1 | Labour: standard rate per hour | — |
l2 | Labour: actual rate paid per hour | — |
l3 | Labour: hours allowed for the actual output | h |
l4 | Labour: hours actually worked | h |
TT | Total variance: actual cost − standard cost (+ = adverse) | — |
MP | Material price variance (+ = adverse) | — |
MU | Material usage variance (+ = adverse) | — |
LR | Labour rate variance (+ = adverse) | — |
LE | Labour efficiency variance (+ = adverse) | — |
Worked example
- Material: standard price per unit2
- Material: actual price paid per unit2.1
- Material: quantity allowed for the actual output500
- Material: quantity actually used520
- Labour: standard rate per hour18
- Labour: actual rate paid per hour19
- Labour: hours allowed for the actual output200 h
- Labour: hours actually worked210 h
- Total variance: actual cost − standard cost (+ = adverse)482.00
- Material price variance (+ = adverse)52.00
- Material usage variance (+ = adverse)40.00
- Labour rate variance (+ = adverse)210.00
- Labour efficiency variance (+ = adverse)180.00
Limitations
- The tool works with whatever currency you use for the inputs; it does not convert between currencies.
- The default values are typical reference figures, not measurements of your situation. Replace them with your own data whenever you have it.