Paritian

Time & Dates

Working Days Calculator

Number of weekdays between two dates, both dates included.

Results

Working days 22
Weekend days 8
Days 30

What this tool does

Counts Monday to Friday and includes both the first and the last day, which is the convention used for project planning and notice periods. Public holidays vary by country and are not deducted — subtract them yourself.

Formula

working days = total days − Saturdays and Sundays

Variables

SymbolMeaningUnit
start_dateStart date
end_dateEnd date
working_daysWorking days
weekend_daysWeekend days
total_daysDays

Worked example

  • Start date2026-09-01
  • End date2026-09-30
  • Working days22
  • Weekend days8
  • Days30

Limitations

  • Only Saturdays and Sundays are excluded. Public holidays differ by country and are not deducted.